TM 9-2320-365-20-2
2-1151
CONTINUITY TEST
(1) Disconnect AC power (TM 9-2320-365-10).
(2) Remove six screws and cover from 110/208
VAC POWER DISTRIBUTION PANEL.
(3) Loosen screw in terminal board TB4.
(4) Remove wire 1499K from terminal board TB4.
(5) Set multimeter to ohms.
(6) Connect positive (+) probe of multimeter to wire
1499K in 110/208 VAC POWER DISTRIBUTION
PANEL.
(7) Connect negative (-) probe of multimeter to wire
1499K in lighting fixture DS83 and note reading
on multimeter.
(8) If continuity is not present, repair or replace
wire 1499K (para 2-40).
(9) If continuity is present, repair or replace wire
3085B (para 2-40).
(9) Install ballast cover on lighting fixture DS83.
(10) Install two fluorescent lamps in lighting fixture
DS83.
(11) Install tube lock holder at each end of two
fluorescent lamps.
(12) Install diffuser on lighting fixture DS83.
(13) Install wire 1499K on terminal board TB4.
(14) Tighten screw in terminal board TB4.
(15) Install cover on 110/208 VAC POWER
DISTRIBUTION PANEL with six screws.
(16) Position circuit breaker CB1 to ON
(TM 9-2320-365-10).
(17) Close door on 110/208 VAC POWER
DISTRIBUTION PANEL (TM 9-2320-365-10).
(18) Connect AC power (TM 9-2320-365-10).