16-51. M1079 FIELD TELEPHONE BINDING POST/BOX AND CONDUIT REPLACEMENT
This task covers:
a. Exterior Field Telephone Binding Post Removal
b. Exterior Field Telephone Binding Post
Installation
c. Interior Field Telephone Binding Post/Box and
Conduit Removal
d. Interior Field Telephone Binding Post/Box and
Conduit Installation
e. Follow-On Maintenance
INITIAL SETUP
Equipment Conditions
Field telephone disconnected (TM 9-2320-365-
10).
AC power disconnected (TM 9-2320-365-10).
Batteries disconnected (para 7-48).
110 vac outlet/box and conduit removed (for
removal of field telephone box or conduit) (para
16-53).
Tools and Special Tools
Tool Kit, Genl Mech (Item 44, Appendix C)
Tool Kit, Auto Fuel and Electrical Systems Repair
(Item 42, Appendix C)
Materials/Parts
Dispenser, Pressure Sensitive Adhesive Tape (Item
21, Appendix D)
Lockwasher (28) (van body serial numbers 001
through 190) (Item 77, Appendix G)
Lockwasher (16) (van bodies serial number 191 and
higher) (Item 77, Appendix G)
Lockwasher (12) (Item 81, Appendix G)
Terminal, Lug (2) (Item 266, Appendix G)
Terminal, Lug (4) (Item 269, Appendix G)
Personnel Required
(2)
a. Exterior Field Telephone Binding Post Removal.
NOTE
Both exterior field telephone binding posts are
removed the same way. Negative exterior field
telephone binding post shown.
Perform step (1) on van body serial numbers
001 through 190.
(1) Remove 28 screws (1), lockwashers (2), washers (3),
and cover (4) from 110/208 vac power entry panel (5).
Discard lockwashers.