TM 9-2320-365-20-3
7-87. WTEC III CAB TRANSMISSION HARNESS REPLACEMENT
This task covers:
a. Removal
b. Installation
c. Follow-On Maintenance
INITIAL SETUP
Equipment Conditions
Instrument panel assembly removed for access (para 7-
15).
Kick panel removed (para 16-3)
Personnel heater removed (para 18-9).
Tools and Special Tools
Tool Kit, Genl Mech (Item 44, Appendix C)
Materials/Parts
Dispenser, Pressure Sensitive Adhesive Tape
(Item 21, Appendix D)
Ties, Cable, Plastic (Item 76, Appendix D)
Lockwasher (4) (Item 67, Appendix G)
Gasket (Item 24, Appendix G)
Personnel Required
(2)
a. Removal.
NOTE
Remove plastic cable ties as required.
Note routing of WTEC III cab transmission
harness prior to removal.
Tag connectors and connection points prior to
disconnecting.
(1) Disconnect connector P119 (1) from connector J119 (2).
NOTE
Step (2) requires the aid of an assistant.
(2) Remove four nuts (3), lockwashers (4), screws (5),
gasket (6), and connector J119 (2) from cab (7). Discard
lockwashers and gasket.
7-376